Construction of Shrine Moves Forward

Announce to friends of East and West that operations commenced last Naw-Rúz on excavation for eight shafts designed for piers supporting the dome of the Báb's Sepulcher terminated. Consignment of thirty-three tons of steel, fifty tons of cement safely delivered to Holy Land. Seven thousand three hundred pound (i.e., Israeli unit of currency) contract for structural work, capable of sustaining the thousand-ton weight of superstructure, signed. First installment out of eight hundred tons of stones for octagon and dome of Shrine recently received. Greatly heartened by response of self-sacrificing believers in both hemispheres enabling energetic prosecution at this critical hour of so holy an enterprise. May sustained support of all communities hasten its glorious consummation.

[May 29, 1951]